Solar street lamps and energy saving, convenient installation, has been widely used. Solar street lamp installation without the underground buried cable, cut down the cost of construction, however, completes the foundation wants before installation pouring solar street lamps, in order to learn more about the relevant knowledge, said solar street lamp installation of foundation casting procedure for today.
for solar street lamps with energy-saving, environmental protection, and the advantages of convenient, now has been widely used. After buy solar street lights will inevitably involve the installation problem, today we are going to learn about the solar installation foundation in the process of casting.
foundation casting steps are as follows:
1, determine the floorlamp location:
survey and geological conditions, if the soft soil 1 m 2 are the surface, so the excavation depth should be deepened; At the same time to confirm the excavation position under no other facilities ( Such as cable, pipes, etc. ) , street lamp at the top of the shade objects for a long time, otherwise it should change the position.
2, in the position of lamps and lanterns (reserved The excavation) Conforms to the standard 1 m 3 pit, embedded parts localization casting:
embedded parts are placed in the square in the middle of the pit, PVC threading pipe end in right in the middle, on the other side of embedded object in the storage battery. Keep the embedded parts, foundation and ground in the same horizontal plane, Or the top of the screw and the original ground in the same horizontal plane, according to the requirements of the site and decide) , one side should be parallel to the road, so can guarantee the light pole erected after correct and not skewed. And then fixed with concrete pouring, casting or stop using vibrator vibration in the process, to ensure that the overall density and robustness.
3, construction completed, clear in time positioning plate residual sludge, and the waste oil cleaning impurity on the bolt.
4, concrete solidification process, water them regularly maintenance; To concrete is set ( Generally more than 72 hours) To install droplight.
about solar street lamp installation foundation is pouring process above, solar lights solar lighting factory zhongshan remind you that the installation pouring to err on the side of street lamp construction foundation, so as to guarantee the late.
solar lamp factory zhongshan solar lighting focus on research and development of solar energy street light ten years, can provide you with professional technical service, to meet your any demand for lighting.