Residents personal family install solar photovoltaic power generation is a distributed photovoltaic power generation. If you want to apply for interconnection, first you need to submit the basic personal information, such as the original and copy of the applicant's identity card; Resident hu kou book, house property card copy or house lease contract, etc.
personal family install distributed photovoltaic solar photovoltaic power generation is a resident. If you want to apply for interconnection, first you need to submit the basic personal information, such as the original and copy of the applicant's identity card; Resident hu kou book, house property card copy or legitimacy support files such as house lease contract; If you are using a public house roof, you need to provide other owners, property management, residents' committees agreed to prove the written documents; Pre-project related information, including the type of distributed power supply power, power generation projects; Distributed power project access application form. In addition, still should be commissioned by the requirement to have an aptitude for electric power design, the construction unit of photovoltaic (pv) power equipment installation, and provide the certificate of qualification.
solar grid-connection process for:
1, apply to the business hall of local power or dial 95598.
2, submit the distributed grid photovoltaic power generation project application form 'and' project system design and implementation of the application materials, the state grid will be officially accepted.
3, state grid according to the project owner, project issued by the grid access scheme.
4, confirm the access system solutions. Apply for grid owner review and confirm the access system solutions.
5, issue a net comment letter, applying for grid opinion letter issued by the owner to get the grid connect network.
6, project approval and project construction, complete photovoltaic panels laying projects such as construction work.
7, apply for grid acceptance and debugging, owner to fill in the distributed photovoltaic power generation project acceptance and commissioning application form.
8, accepts the interconnection acceptance and commissioning; National grid will be the door for owner project acceptance, replacement of meters, and with the owner to sign the power purchase agreement.