Solar street lamps installed - — The foundation pouring 1, determine the floorlamp position; Survey and geological conditions, if the surface of the 1 m 2 are all a hotchpotch of soft soil, the excavation depth should be deepened; At the same time to confirm the excavation position under no other facilities ( Such as cable, pipes, etc. ) , street light at the top of the
to install solar street lamps - — Foundation pouring
1, determine floorlamp position; Survey and geological conditions, if the surface of the 1 m 2 are all a hotchpotch of soft soil, the excavation depth should be deepened; At the same time to confirm the excavation position under no other facilities ( Such as cable, pipes, etc. ) , street lamp at the top of the shade objects for a long time, otherwise it should change the position.
2, reserved at establish the position of lamps and lanterns, The excavation) Conform to the standard 1 m 3 pit; Up with location and casting. Embedded parts are placed in the square in the middle of the pit, PVC threading pipe end in embedded inserts right in the middle, on the other end in the storage battery. Keep the embedded parts, foundation and ground in the same horizontal plane, Or screw in the same horizontal plane with the original ground, according to the requirements of the site and decide) , one side should be parallel to the road; After such Fang Kebao
the light pole erected without deviation. Fixed and then to C20 concrete pouring, casting or stop using vibrator vibration in the process, to ensure that the overall density and robustness.
3, construction completed, clear in time positioning plate residual sludge, and the waste oil cleaning bolt impurities.
4, concrete solidification process, water them regularly maintenance; To concrete is set ( Generally more than 72 hours) To install droplight.