1, before the installation of lifting system will be light, lamp plate to a rod body ( Light plate for monolithic) 。 Pay attention to light upper and lower bearing plate. Lamp panel for split type hoisting installation lamp again after dish which in the main stem. 2, install the steel wire rope: before installation of wire rope through the connection of the main cables
1, before the installation of lifting system will be light,' Light, generally refers to more than 15 meters steel conical light pole and high-power modular fixtures are composed of new type of lighting. 】 Lamp plate to a rod body ( Light plate for monolithic) 。 Pay attention to light upper and lower bearing plate. Lamp panel for split type hoisting installation lamp again after dish which in the main stem.
2, install the steel wire rope: before installation of wire rope will be the main cable through the connection plate of the cable hole, Waterproof connector bucai) In waterproof connector 2 meters of cable clamp equipment, prevent light dish up cable to pull off. Main solar street light steel prices generally how much is a wire rope from the top light pole through until the bottom of the light pole, before using the socket through the nylon rope for traction. Put the steel wire rope coupling plate close to the top of the light pole, respectively from the three wire rope hoist system through flange, from surface wear protective card into the wire rope pulley above, through the inside came out from the other side of the wire rope pulley above, out of the wire rope guide hole wear. Cable through the corresponding pulley arm (also The pulley of the cable is white nylon pulley) Guaranteed not to coiled wire and cable lifting system.
3, will lift system with screws on the top of the light pole, wire and cable inside the lamp post will not be coiled.
4, use screw to install the lightning rod on top of the elevator system, and adjust the lightning rod straightness.