Solar street lamp installation step 1: lamp foundation how to casting

1, determine the floorlamp position; Survey and geological conditions, if the surface of the 1 m 5 are all a hotchpotch of soft soil, the excavation depth should be deepened; At the same time to confirm the excavation position under no other facilities ( Such as cable, pipes, etc. ) , street lamp at the top of the shade objects for a long time, otherwise it should change the position.

2, in the position of the lamp (reserved The excavation) The pit of conform to the standard ( According to the light pole height design depth) ; Embedded parts location and casting ( Concrete pier to cage) 。 Embedded parts are placed in the center of the pit. Keep the embedded parts, foundation and ground in the same horizontal plane, Or the top of the screw and the original ground in the same horizontal plane, according to the requirements of the site and decide) , one side should be parallel to the road, so can guarantee the light pole erected after correct and not skewed. Then to C20 fixed or C25 concrete pouring, casting process or stop using vibrator vibration ( Or use tool against concrete) To ensure the overall density and robustness.

3, construction completed, clear positioning plate residual sludge in a timely manner and to waste oil cleaning bolt impurities ( Can be wrapped in tape, the position of the bolt before construction to prevent excessive magazine attached to the installation progress) 。

4, concrete solidification process, water them regularly maintenance; To concrete is set ( Generally more than 72 hours) To install droplight.

GET IN TOUCH WITH Us
recommended articles
Knowledge News & events Project
ALLTOP Cordially Invites You | Join Us at WETEX 2026 Dubai Solar PV Exhibition to Explore New Opportunities in the Middle East PV & Energy Storage Market!


Exhibition Name: WETEX 2026
Exhibition Dates: October 20–22, 2026
Venue: Dubai World Trade Centre · Dubai, UAE
ALLTOP Booth: 4C14
Warm Invitation | ALLTOP Debuts at the 140th Canton Fair, Jointly Witnessing a New Future of Green Energy

Exhibition Name: The 140th Canton Fair)
Exhibition Dates: October 15–19, 2026
Venue: China Import and Export Fair Complex, Guangzhou, China
ALLTOP Booth: Zone C · Hall 16.4 · Booths C34-C35, D08-D09
Golden Topping-Out Marks a New Milestone, Output Value Exceeds RMB 600 Million! ALLTOP Industrial Park’s 168,800 m² Project Successfully Topped Out

318 Days—Less Than a Year!

At the “Speed of Light,” from Blueprint to Topping-Out.

50.24 mu of Prime Land, 168,366 Square Meters of Intelligent Manufacturing Space,

Annual Output Value at Full Production Exceeding RMB 600 Million.

ALLTOP Speed, Formidable Strength, and a Promising Future!

Golden Topping-Out Shines, Output Value Soars
The Hype Is On! ALLTOP Draws Global Spotlight at the Solar Expo — Join Us for a Chat
SOLAR PV & ENERGY STORAGE WORLD EXPO 2026

Booth No.: 10.2· B551
Time: September 16–18
Address: China Import and Export Fair Complex, Guangzhou, China (No. 382 Yuejiang Middle Road, Haizhu District, Guangzhou)
ALLTOP UGANDA Invites You to Power and Elec Expo 2026

Exhibition Name: Power and Elec Expo 2026

Date: July 9th-11th 2026

Company Name: Alltop Engineering Uganda

Hall No.

Booth No. A45

Venue: UMA Show grounds, Multi-Purpose Hall, Kampala-Uganda
Our aim is to provide the best products and the most considerate service for customers.
About Us
Customer service