High lamp has a large scope of application, with beautiful, adornment sex is strong, lighting area is large, the advantages of good effect, the following follow high lamp manufacturers to know about the light, the laying of the cable problem.
(1) the project introduced outdoor center substation cable adopts YJV22 - Along the cable trench well equipped, across the road depot cable using CDB100/8 FRP cable protection pipe laying. Indoor lighting using BV copper plastic wire wear tight metal steel tube have hidden, wire wear tight dark apply stereotypes of galvanized steel duct laying within the concrete protective layer and the thickness of not less than 30 mm. Enclosed bus run level, not less than 2 high from the ground. 2 m, when the vertical run, apart from the ground 1. 8 m in the following sections to take measures to prevent mechanical damage. Fire the NH - electricity YJV cable, in welded steel pipe and dark apply when laying within the concrete protective layer thickness is not less than 30 mm.
2 cable bend must be greater than the minimum & other; Bending radius & throughout; , that is, 10 times the diameter of the cable.
(3) more cable laying, specifications larger cable first.
(4) cable connector and cable end construction must adopt the method of specification, in the process of laying cable joint 1 shall be maintained. 5 meters allowance. According to the specification of connector to prison, the interface with epoxy resin.
5] cable length one by one check, no cable should be succeeded.
[6] line pipe when the pipe laying in a galvanized iron wire.
once put cable wear of butter or talcum powder. Nozzle is smooth, pay attention to the seal, into the pipe cable should keep straight, and adopt measures to moistureproof, anticorrosion, rodents, etc.