EMC mode case analysis: solar LED road lamp renovation project of fosan buddhist the city zone

by:ALLTOP      2020-12-03
With zen city, foshan city, guangdong province LED street lamp demonstration project as an example, the demonstration project adopts frequently on high power LED street light, Tunnel light) 5659 streetlights of zen city transformation, the project total investment 36 million yuan, divided into two phases. Project launched in November 2008 and December 2009 the second phase of the project completed, complete the transformation. The first phase completed 926 lamp high pressure sodium lamp; The second phase of the transformed to complete 5434 lamp high pressure sodium lamp, two phase of the actual renovation, a total of 6360 completed the LED street lamp light. This project USES frequently on EMC mode, specific operation is as follows:
1. Intention to determine of the project: in 2008, the customer ( The government) And attendance is formed on the LED street lamp renovation preliminary. Unresolved mentioned the LED street light transform the model of EMC problems, frequently on the agreed with the customer, first install LED lights in the model road, entrust a third party professional organization for performance of the LED street lamps, energy-saving rate test, energy-saving benefit calculation, and the results are the two sides confirmed. By the two sides confirmed YangBan Road calculation quantity and power saving rate, the transformation of street lamp power, local electricity price, and other comprehensive factors, calculate the project transformation after the formation of the electricity efficiency.
  2. Project: frequently according to the customer on the street light project and the third party test data of the specialized institutions, for the LED street lamp project project feasibility analysis, feasibility analysis includes technology advanced, street lamp transformation reasonable light distribution, project investment plan, sources of funds, projects running mechanism, social and economic benefit evaluation, etc. ; After the feasibility report as agreed, the project project formally, frequently on the company further project planning and engineering design for the modification of the street lamp.
  3. Capital requirements on the financing of the project: the attendance according to the project, contact with financial institutions, financial institutions, financial ability to pay to the project feasibility report and the customer for review, at the same time in attendance on production capacity and technical level of quality assurance systems, enterprise financial strength, corresponding bank credit status of the inspection, determine to provide project financing, and then by the attendance, customer and financial institutions agreed to finance credit and payment method.
  4. : the contract signing and financial institutions are in basic agreement in all respects, after the contract signed with frequently on customer project, project contract and financial institutions to financing contract. Customers according to project requirements and expected future power saving benefits to determine supply, contract term, repayment method, and both sides profit proportion. Take an equal repayment way this project, the contract is a total of six years, energy-saving benefit sharing the starting date for 1 of the following month after the acceptance of the project, benefit sharing period for six years, customers, EMC company both sides according to the agreed percentage share six years of total energy conservation benefit, frequently on the lamps and lanterns of normal revenues.
  5. Project implementation: the customer pay the attendance on photoelectric LED street lamp project, LED street light energy-saving renovation project started the construction, installation and debugging, project design and achieve the project quality standard to finish on time.
  6. After-sales service: LED street lamp after put into use, frequently on the company responsible for the street lights maintenance work, the customer is responsible for the street lamp operation and energy-saving monitoring work. Frequently on the free replacement product life do 5 years experience in quality assurance commitment and insurance company accept insurance, to ensure that the interests of users and other financial institutions.
  7. Energy-saving benefit sharing: the customer will be a year of electricity saving income and save the maintenance fee income as the total energy conservation project. Customers according to contract agreement with EMC company proportional share the energy saving benefits.